Track cost per a swimlane path
You can track the cost for a swimlane path. The cost shows on top of the lane as a sum of all the step costs multiplied by the number of instances. Pre-condition: you should have a Swimlane chart built on the process.
- Navigate to and select the process that your swimlane is based on.
-
Right-click a step and select
Edit.
The Define process step window appears.
- Set the Step cost and click OK.
- Repeat steps 2 and 3 for each step, as applicable.
- Navigate to and select the view with the swimlane.
- Select the swimlane component.
- In the Property Panel, open Lane caption and select Process cost from the list.
-
Save
the changes.
The process cost appears on top of the lane.