DaysAfterCurrentDate

Description

Specifies the number of days after the current date that the due date can still be considered valid. If a due date is later than that, the field is given Validation error status.

This setting helps ReadSoft Invoices to find the correct due date on invoices. Set it to the maximum number of days from the current date to the due date.

Example:

If the current date is June 30, 2005 and DaysAfterCurrentDate=30, then a due date of July 25 is accepted, but a due date of August 1 is not accepted and the field gets Validation error status.

Valid values

Any integer.