Utilization
|
-
Percentage utilization against availability: The actual
percentage time the resource spent creating jobs and working on activities, for
the time they were available in the simulation. For example, for a one hour
simulation, if a resource was available and busy for 30 minutes their
percentage utilization against availability is 100%, as they were 100% utilized
for the time they were available.
-
Percentage utilization against timeframe: The actual time
the resource spent working against the timeframe (duration) of the simulation.
For example, in a one hour simulation, if a resource was available and busy for
30 minutes their percentage utilization against timeframe is 50%, as they were
busy for half of the duration of the total simulation.
Note Utilization is the amount of time a resource spends in
Busy (actively working on activities) or Creation (the time takes to create
jobs) states.
|